Diagnose schedule delay, rebuild a realistic forecast and compare recovery options through a fully calculated five-activity equipment-setup example.
The running network moves from a nine-day baseline to an eleven-day forecast. Compare confirmed acceleration, technically approved overlap, scope deferral and acceptance of delay, then authorise and monitor the chosen response.
Start with a dated recovery question
A recovery plan must improve the forecast while protecting the required outcome. A misleading update can send recovery effort to the wrong place. The controlling sequence matters more than the largest overdue task list. Use the baseline network as the comparison, not as a substitute for today’s forecast.
A-B-D-E totals 2 + 4 + 2 + 1 = 9 days. A-C-D-E totals 8 days. Under these assumptions, C has one day of float before it delays D.
Calculate the current delay
Forecast from the cutoff using realistic remaining durations. Different causes need different recovery actions. A shorter logical path is useful only if it can be staffed and executed. Crashing trades additional cost for a feasible reduction in duration.
Added cost = 2 x 400 = 800. B finishes at day 6; C at 5; D at 8; E at 9. The option recovers the two-day delay under the stated assumptions.
Option two: overlap suitable work
Fast tracking changes sequencing and can increase rework or coordination risk. A scope trade-off requires an authorised change and an acceptable result. An honest date change can be preferable to an unsafe or uneconomic recovery. A review should compare credible alternatives from the same cutoff.
For each option, show scope, cost, resource commitments, acceptance, residual risks and confidence. Identify any mutually exclusive assumptions or unresolved approvals.
Authorise and integrate the recovery
Make the chosen option executable across the project records. Use short feedback intervals tied to the controlling work. Stakeholders need the delivery consequence and the decision they can make. A complete recovery decision connects diagnosis, feasibility and follow-through.
Options compared on common assumptions; costs and acceptance effects visible; residual risks explained; owner and authority confirmed; chosen conditions secured.
Contents
- Start with a dated recovery question
- Verify the status before intervening
- Rebuild the dependency logic
- Calculate the original finish
- Calculate the current delay
- Diagnose the cause before choosing a remedy
- Check resources and calendars
- Option one: accelerate controlling work
- Option two: overlap suitable work
- Option three: defer lower-value scope
- Option four: accept a revised date
- Compare the options on one basis
- Authorise and integrate the recovery
- Monitor whether recovery is working
- Communicate the situation clearly
- Your recovery desk check
Using the PDF
Each numbered page contains an explanation, an original worked situation and a practical action. The bookmarks navigate the learning pages. A templates advertisement follows content page 5 and a Coursera Plus advertisement follows content page 15. The entire advertisement image is linked. Promotional links may earn Coursya a commission. A purchase is optional.
Frequently asked questions
Who is this guide for?
Diagnose schedule delay, rebuild a realistic forecast and compare recovery options through a fully calculated five-activity equipment-setup example.
How can I practise the ideas?
Follow the running case, work through the page actions and use the PDF bookmarks to revisit a topic. The final learning pages help you apply the decisions to your own project.
What does the download contain?
The PDF contains 19 pages, including 16 numbered learning pages, a cover and two linked advertisements. The book is written in English.