Your Project Is Over Budget: A Guide to Analysis and Corrective Action

Analyse a project cost overrun without double-counting commitments, build a remaining-work forecast and assess a calculated corrective option for an equipment-service pilot.

Cost & Budget Management

Analyse a project cost overrun without double-counting commitments, build a remaining-work forecast and assess a calculated corrective option for an equipment-service pilot.

The case starts with BAC 80,000, total funding 85,000 and a bottom-up EAC of 92,000. Follow the distinction between performance, forecast, funding, reserves and approved corrective action.

Treat overrun as a decision problem

A useful cost response explains the outlook and the choices available. A forecast cannot be stronger than its underlying records. An outstanding order is not always an additional forecast cost. Build ETC from the scope and conditions that still exist.

Remaining supplier work is 18,000; labour 22,000; testing 7,000; and a specifically assessed remaining risk allowance 3,000. ETC = 18,000 + 22,000 + 7,000 + 3,000 = 50,000.

Calculate the completion forecast

Show the amount, percentage and comparison basis together. A ratio can challenge the estimate without replacing a causal review. Connect the amount of the overrun to something you can change. A single EAC does not describe every plausible outcome.

A lower-cost scenario has ETC 46,000; an adverse scenario has ETC 58,000. Adding AC 42,000 gives EACs of 88,000 and 100,000. The reviewed central estimate remains 92,000.

Develop responses that address causes

A useful saving changes future cost without quietly removing required outcomes. Combine savings only when their causes and cost buckets are distinct. A cheaper project can fail if it no longer delivers the needed result. A funding source does not establish that the underlying change is acceptable.

An EAC of 85,000 fits total funding but still needs the appropriate decision on the 5,000 baseline excess and reserve treatment. A forecast figure alone cannot provide that authorisation.

Prepare the decision request

Make the cost problem concrete enough for an authorised choice. Translate the decision into work, purchasing and forecast records. A response succeeds when the result remains acceptable and the forecast is supported. Keep diagnosis, authority and execution connected.

Net savings tested; duplicate benefits removed; scope and acceptance effects clear; funding treatment decided by the proper authority; action owners confirmed.

Contents

  1. Treat overrun as a decision problem
  2. Reconcile the cost cutoff
  3. Separate actuals from commitments
  4. Re-estimate the remaining work
  5. Calculate the completion forecast
  6. Use performance indicators as a cross-check
  7. Find the cost drivers
  8. Check uncertainty and exposure
  9. Develop responses that address causes
  10. Test a combined corrective option
  11. Assess scope and benefit trade-offs
  12. Use reserves through the agreed authority
  13. Prepare the decision request
  14. Implement the approved response
  15. Monitor cost and outcome together
  16. Your cost-correction desk check

Using the PDF

Each numbered page contains an explanation, an original worked situation and a practical action. The bookmarks navigate the learning pages. A templates advertisement follows content page 5 and a Coursera Plus advertisement follows content page 15. The entire advertisement image is linked. Promotional links may earn Coursya a commission. A purchase is optional.

Frequently asked questions

Who is this guide for?

Analyse a project cost overrun without double-counting commitments, build a remaining-work forecast and assess a calculated corrective option for an equipment-service pilot.

How can I practise the ideas?

Follow the running case, work through the page actions and use the PDF bookmarks to revisit a topic. The final learning pages help you apply the decisions to your own project.

What does the download contain?

The PDF contains 19 pages, including 16 numbered learning pages, a cover and two linked advertisements. The book is written in English.