The baseline is 600+480+350+120=1550 direct units and 1705 including the case contingency. In the payment scenario, 200 paid + 880 unpaid commitments + 470 uncommitted forecast = 1550 direct units. At 50 learners, materials become 600, direct costs 1670 and total planned funding 1837.

Critical check: Double-counted commitments, unexplained rates or an unapproved change hidden in the baseline prevent completion.

Final project: Build the Pine budget pack: estimate bases, baseline, obligations/payment reconciliation, attendance-change forecast and a concise sponsor decision note.