At the cut-off, accepted output is 60, not 80. The base forecast is 60+4×10=100, ten below the final target. A final result of 104 is four above that forecast but still six below target. Those two comparisons answer different questions and should not be merged.

Critical check: Do not count unaccepted output as complete, double-count the review queue or rewrite past forecasts after the fact.

Final project: Create the Willow reporting portfolio: reporting contract, measures, forecast scenarios, one-page decision report and close-out note.