The delivery pulse

CASE STATUS: fictional/synthetic teaching material. Do not present the example as real research, employment experience or measured business performance.

OUTCOME
Build a concise project status report that separates evidence, forecasts, issues and decisions, then updates it consistently.

BEFORE YOU START
Basic project vocabulary and arithmetic; no reporting platform is required.

CASE
Willow Archive is digitizing a collection. At the reporting cut-off, 80 items were planned and 60 meet the acceptance check. Twenty more are in review, not yet accepted. The team has four working days remaining and an observed acceptance rate of ten items per day.

INPUTS
Measure,Case value
Planned accepted items at cut-off,80
Actually accepted items,60
"In review, not accepted",20
Observed accepted items per day,10
Days remaining,4
Final target accepted items,110


ENTRY CHECK

Question: Should work awaiting review count as accepted?

Self-check: No. Keep the completion definition consistent.

Question: Is an observed rate a guaranteed future rate?

Self-check: No. Use it as an assumption and test capacity or variability.

Question: What makes a status report actionable?

Self-check: A clear implication, owner and decision or next step.

STAGE 1: Define the reporting contract

Prerequisite: Basic project vocabulary and arithmetic; no reporting platform is required.

Instruction: Agree on the cut-off, completion definition and audience before choosing charts. A report can be internally accurate yet misleading if one team counts submitted items and another counts accepted items. Record the source of each measure and the person responsible for updating it. Keep original observations separate from the interpretation added for the sponsor.

Practice task: Write a reporting specification with cut-off, accepted-item definition, data owner and source. Explain how the 20 review items will appear.

Deliverable: A reporting contract

Acceptance check: The report distinguishes accepted from in-review work and uses one cut-off.

If stuck: If totals conflict, compare definitions and dates before assuming someone made an arithmetic error.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 2: Calculate the variance

Prerequisite: Bring your previous output: A reporting contract

Instruction: A variance compares like with like. Here accepted output is 20 items behind the planned 80 at the cut-off. The completion ratio against the final target is a different calculation. Avoid choosing whichever denominator makes performance appear strongest. Show the denominator beside the number, especially when a percentage is used in a headline.

Practice task: Calculate accepted-versus-plan variance, acceptance against final target and the number still needed. Label each measure in plain language.

Deliverable: A three-measure status table

Acceptance check: Variance is −20; 60/110 is about 54.5%; 50 accepted items remain.

If stuck: If the percentage is 75%, identify that it compares current actual with cut-off plan, not final completion.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 3: Forecast with assumptions

Prerequisite: Bring your previous output: A three-measure status table

Instruction: A simple forecast can reveal a decision without pretending to be a sophisticated model. At ten accepted items per day, four remaining days add 40, giving 100 against a target of 110. State whether review capacity and input quality support that rate. Do not automatically add the 20 in-review items again if the daily acceptance rate already includes review output.

Practice task: Forecast the finish under rates of 8, 10 and 13 items per day. Explain the assumptions and the risk of double counting the review queue.

Deliverable: A three-scenario forecast

Acceptance check: Forecasts are 92, 100 and 112 accepted items, with the rate assumption visible.

If stuck: If the baseline forecast reaches 120, check whether the review queue has been counted twice.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 4: Turn evidence into a decision

Prerequisite: Bring your previous output: A three-scenario forecast

Instruction: A sponsor note should explain what changed, why it matters and what decision is needed. Use an issue for a current obstruction and a risk for an uncertain future event. A red status with no action is only decoration. Present options that affect a real constraint, such as extending the deadline or adding qualified review capacity, and state the trade-off.

Practice task: Write a one-page update with evidence, forecast, one current issue, one risk and two options. Assign an owner and deadline to the decision request.

Deliverable: A sponsor-ready exception report

Acceptance check: The decision request follows from the forecast and does not claim that extra staff instantly increase throughput.

If stuck: If the note is an activity diary, remove completed meetings and retain facts that change a decision.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 5: Close and learn

Prerequisite: Bring your previous output: A sponsor-ready exception report

Instruction: A final report records what was accepted, what remains and who owns the handover. Preserve the reporting history rather than retroactively making forecasts match actual outcomes. A lesson learned should describe a specific condition, consequence and recommended future action. Avoid attributing success or failure to a person without evidence.

Practice task: Simulate a final result of 104 accepted items. Reconcile the target gap, assign remaining work and write one lesson about review capacity.

Deliverable: A close-out and residual-work note

Acceptance check: Six items remain against the target, and the report names their owner and agreed disposition.

If stuck: If the project is labelled complete, explain the acceptance decision and treatment of residual scope.

Record your work, decisions and evidence:




Record your result against the acceptance check:



WORKED CASE
At the cut-off, accepted output is 60, not 80. The base forecast is 60+4×10=100, ten below the final target. A final result of 104 is four above that forecast but still six below target. Those two comparisons answer different questions and should not be merged.

FINAL PROJECT
Create the Willow reporting portfolio: reporting contract, measures, forecast scenarios, one-page decision report and close-out note.

REQUIRED CRITICAL CHECK
Do not count unaccepted output as complete, double-count the review queue or rewrite past forecasts after the fact.

SCORING
Score each of the five stage acceptance checks from 0–16 (0 missing/incorrect; 8 partially supported; 16 complete and evidenced). Score the final integrated project from 0–20 (0 missing; 10 incomplete handover; 20 complete, reproducible and consistent with the case). Target: at least 80/100 AND the critical check must pass. A total score never overrides a failed critical check.

SCOPE LIMIT
This path teaches decision-focused reporting, not earned-value certification or a full project-controls system.

SOURCES AND ACCESS
Assigned public videos can be watched free. Complete the original case in a text editor, on paper or in a spreadsheet you already have. No paid course, exam or provider certificate is included.

Free Project Execution and Tracking Course by Google
WikiFree: https://wikifree.com/courses/google-project-execution-free-video-course/
Official source: https://www.youtube.com/playlist?list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA
Why selected: The tracking, data-storytelling and close-out lessons support the complete reporting lifecycle.

Stage 1 selected lessons:

6. Project Tracking Methods and Examples (36:35)
https://www.youtube.com/watch?v=oLh8akA7F3I&list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA&index=6

Stage 4 selected lessons:

2. Storytelling with Data to Make Decisions (34:53)
https://www.youtube.com/watch?v=4VDRNQ_f4IE&list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA&index=2

Stage 5 selected lessons:

4. How and When to Close a Project (19:22)
https://www.youtube.com/watch?v=wJ5f7TxcPR0&list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA&index=4

REUSE
Original WikiFree teaching text and synthetic fixtures are supplied for personal learning and adaptation with attribution. Provider lessons remain on their original sites and retain their own terms. No provider certificate is included.