Initial expected exposure is 1000 units. Shipment prevention plus residual loss is 200 + 0.10×2000 = 400, compared with 600 untreated. Projector prevention gives 150 + 0.05×3000 = 300, the same expected cost as untreated, but it may protect the opening-day constraint. Buying both costs 350 and fits the 400 prevention budget.

Critical check: A response without an owner or trigger, or a probability presented as a proven frequency, prevents completion.

Final project: Prepare the Maple risk review pack: causal risks, exposure assumptions, selected responses, triggers, contingencies and a simulated review update.