FREE PROJECT RISK MANAGEMENT LEARNING PATH

WikiFree original practice workbook

The risk observatory

CASE STATUS: fictional/synthetic teaching material. Do not present the example as real research, employment experience or measured business performance.

OUTCOME
Create and maintain a risk register with explicit triggers, response choices and a budget-aware contingency plan.

BEFORE YOU START
Basic project concepts and percentages; a spreadsheet is optional.

CASE
Maple Museum is preparing a pop-up exhibit. Its two major uncertainties are a late shipment and projector failure. The figures are fictional planning assumptions, not statistical forecasts.

INPUTS
Risk,Assumed probability,Impact cost,Prevention cost,Residual probability
Late shipment,0.3,2000,200,0.1
Projector failure,0.1,3000,150,0.05
Unexpected crowd,0.2,500,80,0.1


ENTRY CHECK

Question: Is an issue still a risk?

Self-check: A risk is uncertain; an event that has happened becomes an issue requiring action.

Question: Does a probability of 30% mean the loss will be 30% of the impact?

Self-check: No. Expected value is a planning average under assumptions, not the amount of a single outcome.

Question: Can risk be owned by everyone?

Self-check: A named person should coordinate the response even when several people help.

STAGE 1: Write cause, event and effect

Prerequisite: Basic project concepts and percentages; a spreadsheet is optional.

Instruction: A usable risk statement separates why something could happen, the uncertain event and its consequence for the project. Late shipment is a starting label, not a complete analysis. Link the consequence to a named objective, such as opening day or cost. Keep current issues in a separate log so an already missed shipping date does not disappear into a future-risk score.

Practice task: Expand the three case labels into cause–event–effect statements. Add one current issue and explain why its treatment differs.

Deliverable: Three risk statements and one issue entry

Acceptance check: Each risk has an uncertain event and a specific project consequence.

If stuck: Replace labels such as supplier problem with a causal statement that suggests a response.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 2: Compare exposure carefully

Prerequisite: Bring your previous output: Three risk statements and one issue entry

Instruction: Expected monetary exposure multiplies a probability assumption by a monetary impact. It helps compare some options, but it does not capture reputation, safety or a hard opening-date constraint. A qualitative matrix can be useful if the meanings of its labels are explicit. Multiplying arbitrary ordinal labels does not create a precise probability. Preserve the assumptions behind every score.

Practice task: Calculate expected exposure for each risk. Add a separate opening-date impact column and explain one situation in which the largest cost is not the first priority.

Deliverable: An exposure table with assumptions

Acceptance check: Expected costs are 600, 300 and 100; nonfinancial consequences remain visible.

If stuck: If a number appears precise, state the evidence and uncertainty supporting it.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 3: Choose a response

Prerequisite: Bring your previous output: An exposure table with assumptions

Instruction: Compare the prevention cost with the change in expected exposure, then consider feasibility and consequences. A response can reduce likelihood, reduce impact, transfer part of a consequence or accept the exposure. Acceptance still needs a conscious decision. Insurance or a supplier clause may have exclusions; this exercise does not establish legal coverage.

Practice task: Calculate prevention cost plus residual expected loss for all three risks. Recommend responses within a 400-unit prevention budget and explain any constraint-driven exception.

Deliverable: A response selection and budget note

Acceptance check: The chosen prevention costs fit the budget and every residual risk remains recorded.

If stuck: If all responses look worthwhile, rank by goal protection and expected reduction per budget unit.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 4: Define triggers and contingencies

Prerequisite: Bring your previous output: A response selection and budget note

Instruction: A trigger is an observable signal that prompts a specific action. Monitor closely is not a contingency. For the shipment, a missing dispatch confirmation on the agreed date can trigger a backup display plan. Specify the decision owner and the latest useful action time. A response that cannot be started before its benefit disappears is not an operational plan.

Practice task: Create one trigger, owner, action and decision deadline per risk. Separate prevention work from actions taken after the trigger.

Deliverable: A trigger and contingency sheet

Acceptance check: Each trigger can be observed and leads to a named action before it becomes too late.

If stuck: If the owner cannot observe the signal, assign an information source and check frequency.

Record your work, decisions and evidence:




Record your result against the acceptance check:



STAGE 5: Review residual risk

Prerequisite: Bring your previous output: A trigger and contingency sheet

Instruction: Review risk when assumptions, scope or evidence change. If the supplier confirms dispatch, reassess the shipment risk rather than deleting the history. If the projector fails, open an issue and execute the contingency. A register supports decisions only when it records what changed and why. The meeting should focus on exceptions and upcoming trigger dates.

Practice task: Simulate a dispatch confirmation and a projector failure. Update status, owner action and residual exposure, preserving the original assumptions in a change log.

Deliverable: A revised register and decision log

Acceptance check: The happened event is handled as an issue and the remaining uncertainties are reassessed.

If stuck: If the log only changes colors, add the evidence and resulting decision.

Record your work, decisions and evidence:




Record your result against the acceptance check:



WORKED CASE
Initial expected exposure is 1000 units. Shipment prevention plus residual loss is 200 + 0.10×2000 = 400, compared with 600 untreated. Projector prevention gives 150 + 0.05×3000 = 300, the same expected cost as untreated, but it may protect the opening-day constraint. Buying both costs 350 and fits the 400 prevention budget.

FINAL PROJECT
Prepare the Maple risk review pack: causal risks, exposure assumptions, selected responses, triggers, contingencies and a simulated review update.

REQUIRED CRITICAL CHECK
A response without an owner or trigger, or a probability presented as a proven frequency, prevents completion.

SCORING
Score each of the five stage acceptance checks from 0–16 (0 missing/incorrect; 8 partially supported; 16 complete and evidenced). Score the final integrated project from 0–20 (0 missing; 10 incomplete handover; 20 complete, reproducible and consistent with the case). Target: at least 80/100 AND the critical check must pass. A total score never overrides a failed critical check.

SCOPE LIMIT
This is operational project-risk practice, not actuarial, insurance, legal or safety-engineering advice.

SOURCES AND ACCESS
Assigned public videos can be watched free. Complete the original case in a text editor, on paper or in a spreadsheet you already have. No paid course, exam or provider certificate is included.

Free Project Planning Course: Budgets and Risks
WikiFree: https://wikifree.com/courses/google-project-planning-free-video-course/
Official source: https://www.youtube.com/playlist?list=PLTZYG7bZ1u6rleiXxZOifusKwZka2KJRs
Why selected: The focused risk lesson supplies the vocabulary before the original quantitative case.

Free Project Execution and Tracking Course by Google
WikiFree: https://wikifree.com/courses/google-project-execution-free-video-course/
Official source: https://www.youtube.com/playlist?list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA
Why selected: The tracking lesson supports ongoing review rather than treating the register as a one-time document.

Stage 1 selected lessons:

1. Risk Management Basics (29:44)
https://www.youtube.com/watch?v=kXkVV7PFWgE&list=PLTZYG7bZ1u6rleiXxZOifusKwZka2KJRs&index=1

Stage 5 selected lessons:

6. Project Tracking Methods and Examples (36:35)
https://www.youtube.com/watch?v=oLh8akA7F3I&list=PLTZYG7bZ1u6pHAmqR_WefTq1Wps0QgslA&index=6

REUSE
Original WikiFree teaching text and synthetic fixtures are supplied for personal learning and adaptation with attribution. Provider lessons remain on their original sites and retain their own terms. No provider certificate is included.