The original critical path is A–C–D–E: 2+5+2+1=10 days. B has two days of float. When B takes six days, A–B–D–E becomes 11 days, making the project one day later. These results rely on the stated calendar and unlimited-resource assumptions.

Critical check: Do not present a dependency-only calculation as a resource-feasible commitment or silently change the time convention.

Final project: Produce the Oak scheduling pack with dependency diagram, forward/backward calculations, baseline, delay scenario and resource-feasibility note.